Consignment:
Cold HP Separator Drum
Dimension:
16.05 m x 7.7 m x 5.2 m (LxWxH)
Weight:
267 MT
We were involved in the project from the very beginning stages. A detailed route survey was conducted for road transportation from Godrej, Vikhroli Plant to Mumbai Port. Our Transportation team arranged the required number of puller & hydraulic axles well in advance at the Plant Site. Our chartering team took a great effort to find a suitable vessel taking the safety requirements into account, as per the package dimensions.
The Centre of Gravity of the package was an offset, which led to the following thorough Technical Study:
The package was placed on Goldhofer hydraulic axles under extreme supervision & it was successfully brought out of Godrej Gate. The large package dimensions required overnight movement through the congested city. Our escort team successfully brought the package near Mumbai Port Gate within 2 days.
Keeping in mind the package dimension, the Mumbai Port Gate needed civil work and some dismantling which we executed in record time. Our Team finally brought the package inside Mumbai Port the same day when the vessel Orient Pluto berthed.
The massive workload was to lift the package under the vessel’s hook as there were no lifting points. The 2 cranes were very close, but with proper coordination with the crane operator, we were able to lift the package & successfully place it under the vessel deck with adequate soft slings.
The sea transportation to Haldia Port was a smooth operation monitored by our Team. The Package was successfully loaded on Goldhofer Hydraulic axles under the vessel’s hook at Haldia Port.
The movement from Haldia Port to IOCL, Haldia Refinery was a big task due to high congestion and shutdown of Electrified Railway Crossing and Transmission line which was done in record time by our expertise.
Total Movements Team was able to deliver the package to IOCL, Haldia Refinery Site well in advance.